Lincoln Avenue Streetscape Update 12/2/2022

Our office recently attended a site survey meeting / walk through regarding the Lincoln Avenue Streetscape project. Work has now concluded for the winter and will resume next spring, as weather permits. All traffic lanes will be open until the work resumes. There are many spots with temporary pavement that will be finished in the spring. There are also several tree openings that will receive new trees once the weather is more conducive for planting. Please contact our office with any questions or concerns.




Recent Posts

See All

Due to cold weather last week, a few items were affected and could not be performed or delayed. The plan to open the bridge and sidewalk is delayed from 11/30/2022 to approximately 12/12/2022. Outside

This week, several sewer lining projects started in our ward. This project will rehabilitate the existing sewer the area without the conventional digging method. This sewer rehabilitation will minimiz