Webster Avenue Bridge Updates

Work on the Webster Ave. bridge continues. Here is what to expect for October. Please note that sidewalks remain closed and the northbound curb lane of Ashland closed starting Monday 10/10/22 for a 4-6 week duration. CDOT is expecting all work to be done by the end of November. Crews will continue working on bridge sidewalks, finish the steel work, place concrete at the west fixed span deck (East side was done in September). They will also finish up electrical work, replace bridge center locks, install new navigational lights for river traffic, install ladders, and new fencing on Ashland.