Wicker Park Bucktown Peoples Gas Project UPDATE

Peoples Gas' Milwaukee project is a System Improvement project from Division to Fullerton to be completed in 4 phases.


COMPLETED: Phase 1 began last year and will be completed this spring. It is mostly small diameter main in Honore from North to Armitage to provide a back feed to the area.


WE'RE HERE --> Phase 2 is insertion of a new gas main in Milwaukee from Division to Wabansia with some small diameter work on Honore and Elk Grove to avoid the intersection of Damen/Milwaukee/North. This will start after phase 1 is complete. This will impact bike lanes, sidewalks, and parking.


Phase 3 is continuing the insertion in Milwaukee from Wabansia to Maplewood. This work can run concurrently with phase 2.


Phase 4 continues to Fullerton and will be constructed in 2022.


Tentative Schedule:


Phase 2 May 2021 through October 2021.

Phase 3 August 2021 through May 2022.

Phase 4 March 2022 through August 2022.

Recent Posts

See All

The Chicago Department of Transportation (CDOT) is scheduled to initiate the following alley and street resurfacing projects over the next several days. The schedule is an estimate, as factors such as

The Chicago Department of Transportation (CDOT) is slated to begin an arterial street resurfacing project on Diversey between Western and Leavitt beginning on August 1, 2023. In advance of this work,

bottom of page