Dickens Water Project
Work Progress & Tentative Schedule – Week of April 27th, 2026
All new 8” water main pipe has been installed and is 100% completed including the final connection at Dickens and Avondale.
All water services have been transferred from the existing water main to the new main, and lead service line replacements (LSLR) have been completed as part of the program.
DWM crews started demobilizing and will be 100% out of the site by Monday 4/27/2026.
Restoration work is planned to start mid next week and should be done within 45 days of starting.