Greenview Water Project
Greenview, Fullerton to Altgeld
​
Tentative schedule for the week of June 22 (All field activities are weather dependent) -
​
• The new 8” ductile iron water main installation has been completed on Greenview from Altgeld to Fullerton.
• All PDs (Private Drains) on the east side of Greenview have been completed and replaced in accordance with IEPA requirements.
• Approximately 99% of the overall piping work has been completed.
• The Fire Hydrant at 2415 was installed.
• The two-day chlorination process for the new 8” water main was performed from 6/17/26 through 6/18/26.
• The tree at 2415 N Greenview needs to be removed to facilitate the water main transfer. The alley entrance will be closed when the tree removal team arrives.
• Depending on chlorination’s results, crews will start service transfers to the new water main.
In addition to contacting our office with questions, residents can look for a Water Department supervisor on the street wearing a white hard hat to have questions answered immediately.