Water main status: All dry pipe completed from Diversey to Fullerton Water service transfers completed from Diversey to Logan. This week: Testing and disinfection of the new water main completed from Logan to Fullerton Next week: Begin water service transfers from Logan to Fullerton Lane closure and traffic control: Next week: Southbound lanes closed during construction (9am-4pm). Open lane each direction available on the existing NB lanes during construction (Logan to Fullerton) Water main shut downs: Next week: Individual shut downs to occur from Logan to Fullerton during water service transfers. Residents will receive written notice 5 days prior to scheduled shut down.