Update 6/24/22: Water Project on California



Water main excavation:

All dry pipe connections are completed from Diversey to Fullerton. Water service transfers were completed from Diversey to Logan.

Work will be delayed as all sewer work is inspected and reviewed.

Lane closure and traffic control: There will be some temporary closures at a few locations for trench maintenance.

Recent Posts

See All

Due to cold weather last week, a few items were affected and could not be performed or delayed. The plan to open the bridge and sidewalk is delayed from 11/30/2022 to approximately 12/12/2022. Outside