California Water Main Project Update 10/14/2022

Water main status: Next week: Completed final connection at Fullerton on 10/18/22 (water shut down should not impact residents) Restoration status: Next week: Restoration from Logan to Fullerton expected to start week of 10/21/22 Lane closure and traffic control: Southbound lanes closed during construction (9am-4pm). Open lane each direction available on the existing NB lanes during construction (Logan to Fullerton) Next week: Pending restoration schedule Water main shut downs: All water service transfer work has been completed and there are no more water interruptions scheduled.