Fletcher Water Project

Work Progress & Tentative Schedule – Week of February 16, 2026

 

Fletcher (Between Oakley and Hoyne)

​

Monday (02/16/26): Final connection at Hoyne and catch basin outlet installation

Tuesday (02/17/26): Final connection at Hoyne and catch basin outlet installation

Wednesday - Friday (02/18/26 -02/20/26): Private drain replacement

 

 

 

Water Service Interruptions:

 

Scheduled water main shutdown on Monday 02/16/2026 on Hoyne between Belmont and Wellington at 01:00 PM until the work is completed. DWM will provide advance notice before service interruptions.

 

 

Traffic & Parking Impacts:

 

No parking will be allowed within the active work zone during construction hours.

 

Hoyne Ave from Belmont to Barry will be closed during construction hours on Monday and Tuesday.

 

 

In addition to contacting our office with questions, residents can look for a crew member on the street wearing a white hard hat to have questions answered immediately. 

White32Waguespack_LOGO_noweb_2016.png

© 2025 by 32nd Ward Alderman Scott Waguespack.

2657 N. Clybourn, Chicago, IL 60614

Tel: 773-248-1330

Office Hours:
Monday - Friday
9 am until 6 pm

  • Twitter
bottom of page