top of page

Fletcher Water Project

Work Progress & Tentative Schedule – Week of February 23, 2026

 

There are still five private drains that need to be replaced for this project. Other than these, restoration of the street, sidewalks, and parkways will be starting. The street will have a concrete cap until the asphalt plants open in the spring.

​

The concrete work should start in the next 2 weeks after the remaining PDs are completed.  Landscape, paving, and final restoration will occur between 4/20/26 and 6/5/26, dependent on asphalt plant opening dates.

White32Waguespack_LOGO_noweb_2016.png

© 2025 by 32nd Ward Alderman Scott Waguespack.

2657 N. Clybourn, Chicago, IL 60614

Tel: 773-248-1330

Office Hours:
Monday - Friday
9 am until 6 pm

  • Twitter
bottom of page